Legionowo Overpass
01
prevnext

Lead time: 10. 2007 – 12. 2009
Main Contractor: Mosty - Płock

Scope of works supervised:

  • Demolition of the existing overpass: length 404.86 m; width 15.28 m
  • Construction of 2 parallel overpasses, each 183 m long and 10.66 wide
  • Reconstruction of the existing and addition of the second carriageway of 0.875 km long section of No. 61 National Road
  • Reconstruction and upgrading of road systems and road furniture:
    • Sanitary sewage system
    • Storm-water drainage
    • Electricity power lines
    • Water supply and distribution network
    • Heat distribution network
    • Gas grid
    • Telecommunication network